Just as the most recent doomed and daft anti Hs2 Parliamentary petition enters its final week with just 16,000 signatures someone’s gone and started yet another one! This embarrassment of riches won’t stop Hs2 in the slightest of course, but it will give me another 6 months to crunch the numbers and analyse just how weak and how local to the route the remaining opposition to Hs2 is!
The first petition was daft in that it called for Hs2 funding to be diverted to giving everyone free solar panels. This new one’s equally daft and very naive in that it calls for the following;

The idea that the Government will ditch the long-held principle of collective Cabinet responsibility is, frankly, daft. As is the idea that a free vote will result in a majority of MPs suddenly doing a volte-face to vote down building Hs2! Somehow, I can’t see many MPs deciding to deprive their constituents of the economic and transport benefits of Hs2 because of a dwindling bunch of Nimbys in the Chilterns.
The petition has been started by the Editor of the Bucks Herald, one Hayley O’ Keeffe, in what’s little more than a thinly veiled attempt to keep her declining paper relevant, and presumably to try and drum up a few new readers and provide clickbait. Like most local papers the Herald is struggling and its circulation is no longer audited by the Audited Bureau of Circulation, so ABC figures aren’t available. The petition’s not exactly getting off to a stellar start, despite the Herald and others trying to flog it to folk. At the time of writing this it had all of 153 signatures…
Ms O’ Keeffe clearly hasn’t thought this one through, or what these petitions reveal as they’re very much a double-edged sword. Perhaps she should have read my blog on an earlier doomed petition that was stated by StopHs2’s Joe Rukin which you can find here.
I’ll crunch the numbers on the first petition when it finally runs out of rope next Thursday. I’ll carry out a constituency by constituency comparison with the 2018 petition as the decline in numbers should be quite interesting. Then, when Ms O’ Keeffe’s petition runs out of steam on the 17th October I’ll add that too! Of course, by then construction of Hs2 could already have started and many more people living along the routes will have had their properties purchased – further weakening an already tiny opposition. Watch this space!
UPDATE. 18th April.
My comments about the Bucks Herald’s pointless petition have obviously hit a nerve with the paper’s Editor, although misspelling her name seems to have attracted the greatest ire! I received this tweet this morning.

Here’s some of the correspondence that ensued with a link to Ms O’ Keeffe’s valedictory piece.

Ms O’ Keeffe doubles down on the costs ‘spiralling out of control’ spin, which is troubling as you’d hope that a newspaper Editor could tell the difference between fact and speculation and report accordingly. Apparently not.
The fact is – despite whatever fanciful claims a few minutes on Google might throw up – the budget envelope for HS2 hasn’t changed since 2015! It remains at £55.7bn, as detailed on page 16 in this Hs2 document from July 2017.

Has anything changed since? No, the budget envelope remains exactly the same although some costs within it have changed as the designs are refined and new information (such as ground conditions) comes to light . Clearly, this is not the same as ‘costs spiralling out of control’ but that’s the difference between fact and speculation – which is what any of the other figures for the ‘true’ costs of HS2 you’ll find on the internet are.
The breakdown and allocation of costs within the overall funding envelope will be officially updated later this year. Until they are, any figures bandied around on the internet are pure speculation and/or mischief-making. Again, something you’d expect a responsible journalist to report accurately. As for “dire predictions”, so what? Any fool can bandy around numbers.
And what of Ms O’ Keeffe’s petition? It’s got off to a less than stellar start. Here’s the position at 11:15 on Thursday 18th April…

I’ve a favour to ask…
If you enjoy reading this blog, please click on one or two of the adverts. The revenue I receive from this helps me cover the costs of my WordPress site. Many thanks!













08:05We’re now bowling along towards Grantham through the gloom and murk as the haze is sticking with us, which isn’t exactly condusive to good photography!I was surprised to see how many folk on my train were commuting from Leeds to Doncaster. No doubt some were rail staff, but I wonder about the others as you don’t exactly see ‘Donny’ as a thriving centre of commerce.09:05The closer I get to London the worse the murk gets! We’ve just passed Hitchin and visibility is down to 200 metres. If it’s no better in London I may need to rethink my plans for the rest of the day as it’s grim down South. One of my community rail friends has just sent me a picture of sunny Accrington to cheer me up!10:38My luck’s changing at last. The wet weather I was greeted with has changed an the skies are starting to clear. Meanwhile, a friend at Hornsey depot is keeping me abreast of preparations to tow away the first Class 313 (026) to South Wales and the scrap yard. Here it is passing through Finsbury Park on its final journey, hauled by 57312.
Tomorrow night, sister unit 313055 is due to head in the opposite direction, from Hornsey to Yorkshire, where the unit will be scrapped.Here’s the new order that will replace them, seen at Hornsey earlier. The Siemens built Class 717s are a step-change in quality compared to the 1970s designed 313s.
13:00.Due to the weather I didn’t hang around in London. I began heading North, looking for sunshine. I found it at Bedford, on the Midland Main Line, where these units working the Bedford-Bletchley line are due to be replaced by Vivarail Class 230s very soon.
Of course, the times have changed here earlier now that Thameslink are running an entirely new fleet to Bedford.15:36.Northward, ever Northward! My next stop was at Wellingborough to check out progress on both MML electrification and also the massive housing development that’s being built to the North and East of the station. Here’s the view looking North, with the old Midland Railway steam loco shed to the right.
17:22.I’d hopped my way up the Midland Main Line as far as Sheffield where I couldn’t resist stopping for a swift beer in the magnificent Sheffield Tap, which gave me time to upload a few more pictures to the blog. Now I’m heading for Leeds on one of Cross-country’s HST’s which are rather a contrast to the one I started the day on! All the way North the weather’s been a patchwork quilt that’s alternated between sunshine and low clouds or haze. Still, it’s mission accomplished – despite the weather and the all-invasive Buddleia! As someone who spent many years travelling on the old Class 313s I wanted to record the beginning of their end. I only hope GN give the last one’s a proper send-off as they’ve moved millions of people in years they’ve served the railways.17:55I made the cardinal error of using one of the toilets on this train only to find coach C has run out of water, so the sight greeting you in the toilet bowl can be imagined. I’m at Leeds. This trains going all the way to Glasgow and there’s no chance of replenishing the water supply…
18:22.The last train of the day is a refurbished Northern Class 158 that’s taking me and dozens of other weary commuters home. Like every commuter service, no-one’s window-gazing, they see this view 10 times a week at least! Instead, the vast majority are staring at screens of varying sizes and I’ve only heard the rustle of a single newspaper. One or two are taking the chance to doze. All this means it’s a very quiet train…