• About

Paul Bigland

~ Blogging on transport, travel & whatever takes my fancy.

Paul Bigland

Category Archives: Buckinghamshire

HS2’s Wendover Dean viaduct.

14 Friday Jun 2024

Posted by Paul Bigland in Buckinghamshire, Hs2, Photography, Rail Investment, Railways

≈ Leave a comment

Tags

bridges, Buckinghamshire, Engineering, History, Hs2, Photography, Railways, Transport, Travel

*I originally wrote this as an article in RAIL magazine, where it appeared in April 2024.*

One complaint that’s levelled at the new HS2 railway is that it’s hardly going to be Britain’s most scenic rail journey! With 105km of tunnels on the section between London and Birmingham that’s no surprise. Much of the rest will be in cuttings. HS2 will be Britain’s most invisible railway. But there are a few structures that will afford views from the train (however fleeting) as well as provide iconic landmarks that can be admired from afar.

One such structure is the Wendover Dean viaduct which is being built just a few Km South of the town. In January RAIL was invited to take a look at construction progress in the week after the first 90 metre section of the deck had been pushed out onto the piers that will carry it. It’s an impressive structure which crosses above Durham Farm, a portion of Bowood Lane (which is being realingned) and parallels King’s Lane – which will allow views down over the structure. 

A crane used to lift the infill panels into place. A stack of panels can be seen in the foreground. This view is looking South.

Built by EKFB with ASC (Arcadis, Setec, Cowi JV) as its design partner and Moxon as the architects the design has used as inspiration similar French structures like the Vicoin viaduct on the LGV Bretagne – Pays de la Loire high-speed line. When complete the viaduct will be 450m long, sitting on nine piers, some of which are 14 meters high, giving the structure a maximum height of 20 meters (not counting OLE masts). This method of construction is well known in Europe but it’s a first for the UK.

Traditional decks tend to use what is effectively a continuous block of concrete. A drawback of this is that concrete manufacturing is one of the most carbon-intensive parts of such structures. Instead of being constructed of concrete sections built in situ before lifted atop the piers then fixed together, at the Wendover Dean site, EKFB is using a pair of long ‘I’ beams of weathering steel sandwiched between two slabs of concrete with a hollow inner. These beams are constructed by specialists in France before being delivered to the Wendover site in 25 metre sections. They’re then welded together at ground level on the launching platform – a much safer method than having to do it in-situ at height.

This double composite structure is both super strong and lightweight. Compared to the traditional method (pre-cast concrete beams lifted into position with cranes) the overall carbon footprint gives a carbon reduction of 56% over the lifetime of the project. Most of this is in the materials themselves, with transport the next largest contributor. This method should save an estimated 7,433 tonnes of embodied carbon – the equivalent of someone taking 20,500 return flights from London to Edinburgh.

Another interesting aspect of the engineering is the nine piers that will support the deck. The foundations (piling began in June 2022) themselves aren’t unusual They consist of four piles between 38-45 meters deep. A steel cage is inserted into each borehole before being filled with concrete, then topped with a pile cap. Then, a steel cage is built above the pile cap with pre-cast concrete shells slotted over them. Finally, a hammerhead shaped shell is added as the final piece, with a steel cage dropped into it before the shell is filled with concrete. Having these pre-cast concrete shells made off-site at a facility in Northern Ireland is one of the ways that HS2 has managed to reduce disruption to the local area in Wendover as well as control the quality of the finish compared to being built on-site. It’s also a good illustration of how HS2 is generating jobs and income right across the UK, not just on the route. Northern Ireland’s contribution to the project amounts to £140 million in tier two contracts.

Looking North from atop one of the piers. The haul road can be seen to the right of the picture. The red structure on the end of the girders is there to allow the permeant bridge to be guided into place.
The first section after being pushed into place, with some of the infill panels already positioned.

The deck is being assembled in three stages ranging from 90m to 180m sections, with each one pushed out from the north abutment before the next section is attached behind it. This slow and painstaking process means that the weight of the deck will increase with each push, up from an initial 590 tonnes to 3700 tonnes by the end of the year. With the deck moving at roughly 9m/hour, the process will take most of 12 months with the finish point at the South abutment approximately 1.8m higher than start point. The deck is pushed out over temporary bearings, sliding across Teflon plates which are fed across the bearings by hand. Pushing power is provided by cable winches which are anchored to the massive Northern abutment which was specially designed for this purpose – hence its size and weight.

Looking South from the Northern abutment.

When you visit the site you appreciate just how constrained the layout is. The HS2 Hybrid bill defined the limit of land that could be used to built HS2. As you’d expect at a viaduct site, this is quite narrow with most of the site to the West of the viaduct. There’s just enough room to store the concrete panels that form the top and bottom of the viaduct as well as the plant and other machinery needed for construction, plus the offices and welfare facilities which are on a temporary site nearby. One difficulty is the need for a haul-road to pass by the site. This is to allow for the movement of spoil from constructing cuttings to the South towards Wendover where it will be reused. To do this an extra strip of land had to be purchased to the East of the trace so that wagons could traverse the site without interrupting work on the viaduct. This land will be returned to its owners once work is finished.

Looking South from atop one of the piers. The wood on the horizon to the left of the pier is the (in)famous Jones’ hill woods which anti HS2 protestors occupied whilst falsely claiming it had a link to Roald Dahl. Their abandoned camp still lies there, rotting, polluting the very woods they claimed to have been trying to ‘save’.

Our visit allowed access to the top of one of the piers where we had a grandstand view of construction and an impression of how the viaduct was set in the landscape. On the edge of the rise to the South-East corner is the (in)famous Jones’ Hill ancient woodland, the edge of which (0.7 Ha) had to be felled for HS2. This privately-owned wood had been occupied by protesters who falsely claimed it was linked to author Roald Dahl. Their camp still exists, abandoned and rotting, polluting the very land they claimed to be trying to ‘save’. In mitigation, HS2’s planted 4.1 Ha of mixed woodland, some of which is adjacent to Jones’ Hill.

Seeing the red-painted launching-girder attached to the bridge deck at eye-level is quite a sight, as is knowing you’re standing atop a pier that will soon be carrying high-speed trains between London and Birmingham. Our guides also took us to the Northern abutment to see the temporary bearings and show us the Teflon plates that were used as flat rollers, allowing the weathered steel beams to be launched Southwards. Once the completed deck is in place it will rest on jacks which will gradually lower the whole structure onto the permanent bearings that will support it thereafter.

One of the temporary bearings used whilst the bridge deck is pushed out.
Demonstrating how the Teflon plates are used to slide the bridge girders along the structure.

After the main viaduct deck is complete the parapets will be installed along with derailment walling and noise barriers. The parapets will be creased rather than flat. The crease will create inward and outward leaning surfaces that catch light and shade making the structure much more interesting, attractive (and photogenic). Once the civils side is finished the structure will be handed over to the rail systems teams to allow track, signalling and overheads to be installed.

Finally, the adjacent historic field boundaries and hedgerows will be recreated to provide uninterrupted access for farmers and local residents, leaving little to no trace of the construction compound and years of activity.

I suspect this viaduct will become a popular site for photography as it’ll be one of the very few locations where HS2 will be able to be seen in the context of the landscape it passes through. The sight of 400m long trains whizzing through the Chilterns atop a viaduct at speed will be one not to be missed!

I’ve a small favour to ask…
If you enjoy reading this or any of the other blogs I’ve written, please click on an advert or two. You don’t have to buy anything you don’t want to of course – although if you did find something that tickled your fancy that would be fab! – but the revenue from them helps me to cover some of the cost of maintaining this site (which isn’t cheap and comes out of my own pocket). Remember, 99% of the pictures used in my blogs can be purchased as prints from my other website –  https://paulbigland.zenfolio.com/

Or – you can now buy me a coffee! https://ko-fi.com/paulbigland68312

Rolling blog. Wending my way to Wendover…

11 Thursday Jan 2024

Posted by Paul Bigland in Buckinghamshire, Hs2, London, Photography, Railways, Rolling blogs, Travel, West Yorkshire

≈ Leave a comment

Tags

Buckinghamshire, London, Photography, Railways, Rolling blogs, Travel

06:25.

04:15, what a time to be alive! Well, half asleep really as that was the time my alarm clock went off this morning. Dragging my bones out of bed I had an hour to prepare and get myself out of the door before beginning my walk to the station. To be honest, it was one of the best strolls I’ve had for a while. I was in no hurry and the weather was mild (3 degrees) and dry. Whilst strolling up the hill to Spring Edge I looked back across the Calder Valley and the lights of Sowerby Bridge which looked lovely and peaceful. I was momentarily confused when I saw the lights of a 6-car train wending its way below me as nothing should have been running. Then it revved up its engines and the distinctive deep roar reverberating across a sleepy valley gave away the fact this was a pair of Trans-Pennine Class 185s on a diversion. I didn’t pass a soul on the way into town. Even the dog-walkers and their pets were still abed. Even the roads were quiet with just the occasional motorist around. Actually, it really was a good time to be alive…

The centre of Halifax at 05:30. Not a creature was stirring…

Now I’m on Northern’s 05:59 to Leeds. Despite the hour it’s a busy train. Dozens of folk were waiting to catch it at Halifax and many more have joined at Bradford Interchange. Of the 15 seats in the back of the rear car 11 are occupied. I suspect they may fill up before Leeds…

06:50.

My Hebden Bridge – Leeds train was early into Leeds, a rare event as normally you expect to be held outside waiting for a platform, but at this time of day there’s less chance of delays having accrued. This was fortunate as I managed to get ahead of myself by 20 minutes as I made a connection with LNER’s 06:40 to Kings Cross. I’ve now got the mobile office set up in a table bay ready to catch up with the day. At this point I’ve realised the flask of coffee I made to bring with me is still sitting on the kitchen work surface back at home. Bugger! Off to the on-board shop it is then…

08:25.

The arrival of dawn coincided with us passing Peterborough at speed. Supposedly, the days are getting longer but that’s not how it felt today. Now we’re bowling along South of St Neots in half-light past flooded fields that bare testament to just how much rain we’ve been having these past couple of months. The sun’s doing its best to break through the low, patch cloud so I’m optimistic we might get some good weather in Wendover by the time I get there. In the meantime, it’s warm and cosy aboard this train for the next 20 odd minutes before we reach London…

08:30.

I’m always fascinated by the way the weather works. After passing Hitchin we crossed into what’s obviously been a cold front. Everywhere (houses, cars and fields) is coated in a layer of frost so thick you could almost mistake it for a light dusting of snow. What a difference to the mild weather I had on my walk this morning!

08:40.

We’re in the North London suburbs. Having broken through the layer of cloud bordering the capital we’re once more enjoying clear blue skies.

09:55.

On arrival at Kings Cross I transferred to the ‘tube’, or in this case the old Metropolitan line which isn’t a tube at all. An uncrowded train deposited me at Baker St, a station whose architecture and detail I’ve always admired. I was in no hurry so whilst humming Gerry Rafferty’s musical homage I took pictures of the remnants of a more genteel and less rushed age.

Now I’m at Marylebone, waiting for my train to depart, having swum against the tide of incoming commuters. Marylebone has always been the odd one out of London’s termini. It still is today as it’s the only one that’s purely diesel powered – with no sign of electrification in sight…

10:40.

Almost there. The journey onChiltern’s been fine but by God their old ‘Thames Turbo’ fleet is looking tired. The seat coverings are threadbare, vestibule doors are missing and the whole train needs a damned good clean.

17:00.

Apologies for absence but it’s been another busy (if Baltic) day looking at the start of the Wendover viaduct deck push-out. I’ll describe it in more detail later, right now I’m on a train from Banbury into Birmingham have explored a couple of other HS and E-W rail sites with a friend (Chris Howe). In the meantime, here’s a couple of pictures to be getting on with.

The Wendover viaduct looking South. In the background (below the crane) is Jones’ Hill wood.
The view from atop one of the bridge pillars looking North towards Wendover.
Looking South from atop the same pillar. The construction site is long and very narrow. The track to the left is the haul road used for moving spoil from further South to be reused North of Wendover.

I’ve a small favour to ask…
If you enjoy reading this or any of the other blogs I’ve written, please click on an advert or two. You don’t have to buy anything you don’t want to of course – although if you did find something that tickled your fancy that would be fab! – but the revenue from them helps me to cover some of the cost of maintaining this site (which isn’t cheap and comes out of my own pocket). Remember, 99% of the pictures used in my blogs can be purchased as prints from my other website –  https://paulbigland.zenfolio.com/

Or – you can now buy me a coffee! https://ko-fi.cozm/paulbigland68312

The Cinderella line has a fairy Godmother!

19 Tuesday Dec 2023

Posted by Paul Bigland in Buckinghamshire, Photography, Rail Investment, Railways

≈ Leave a comment

Tags

Buckinghamshire, Hs2, news, Photography, Rail Investment, Railways, Transport, Travel

This article originally appeared in RAIL magazine back in October 2023.

Built as a single track line by the Wycombe Railway and opened in 1879, the line between Princes Risborough and Aylesbury has always been a bit of a Cinderella line. Its only claim to fame was the fact it was the last place in the UK to run BR built Class 121 ‘bubble cars’ which were finally retired in May 2017, having been introduced to the line by Chiltern railways in 2003. However, thanks to the arrival of Phase 1 of High Speed 2, this sleepy backwater’s currently having a makeover. HS2 will pass under the existing line to the West of Aylesbury. To do so the EKFB Alliance and Network rail have closed the line from August 19th until the 30th October. The closure has allowed a culvert close to Aylesbury to be rebuilt and a new 1.8km long embankment and bridge to be constructed to replace the 1879 formation. To future-proof the line the new bridge can carry two tracks and the linespeed has been raised from 40 to 90mph. Unlike other bridges on or over HS2, this bridge has been built by sinking four 2.4m diameter piled piers to a depth of 57 meters, making them the biggest piers on HS2. Each pier took between 36-48 hours to pour.  Atop the piers sits a 100m long double-track width steel bridge which was built in 30m sections in the North-East before being transported South and assembled on site. To complete the work Network Rail has used 3000 sleepers and 14,000 tonnes of fresh ballast on the new alignment. A high-output track laying machine installed the rails over a single weekend. 

When I visited on September 25th 2023 Colas Rail had begun tamping the new track ready for the lines reopening. Once tamping is complete 200 tonnes of check-rails will be installed on the bridge to mitigate against the chance of any possible derailment on the bridge affecting HS2 services.  Meanwhile EKFB had begun excavating the clay underneath the bridge to form the HS2 cutting which is exposing the top 8 meters of the piers. This bridge is unique amongst HS2 bridges in that it was constructed at ground level and then the ground’s being dug out from underneath it.

The new bridge on the Aylesbury-Princes Risborough line with excavators beginning to dig out the route of HS2. This view’s looking South towards London
Beginning to excavate around the bridge piers.
The first few meters of a pier’s exposed.

The excavation work’s being done in stages from the North to the South due to the proximity of the old railway formation which still carries fibre-optic signalling cables and has the disconnected track still in situ which will be recovered at a later date. On the South of the old formation EKFB are building the piers and deck of a road bridge over HS2 as passive provision for the South-East Aylesbury Link Road (SEALR) whilst another road bridge over HS2’s being built further to the North-West as part of another link road scheme. 

The new bridge with track in situ looking towards Aylesbury.
Check rails waiting to be installed on the bridge after the line’s been tamped and levelled.
In the foreground is the old railway line. Behind it in the light coloured troughing are the signalling cables which have been lifted and protected whilst work goes on.
Looking South from the new railway bridge along the trace of HS2 towards London.
The Colas tamper waits to begin work. In the foreground is one of the new culverts which improve drainage on the Aylesbury-Princes Risborough line.
This photo gives a better impression of the length of the new bridge over HS2.

Future work to the line will see the half-barrier level crossing at Marsh Lane near Little Kimble upgraded and replaced with full-width barriers (which will allow linespeed improvements) and resignalling.

I’ve a small favour to ask…
If you enjoy reading this or any of the other blogs I’ve written, please click on an advert or two. You don’t have to buy anything you don’t want to of course – although if you did find something that tickled your fancy that would be fab! – but the revenue from them helps me to cover some of the cost of maintaining this site (which isn’t cheap and comes out of my own pocket). Remember, 99% of the pictures used in my blogs can be purchased as prints from my other website –  https://paulbigland.zenfolio.com/

Or – you can now buy me a coffee! https://ko-fi.com/paulbigland68312

Recent Posts

  • Rolling blog. Christmas carolling…
  • 17th December picture(s) of the day…
  • 15th December picture of the day…
  • TRU update. Batley to Ravensthorpe.
  • 9th December picture of the day…

Recent Comments

ramakrishnanaidu400's avatarramakrishnanaidu400 on London, HS2 and home…
Paul Bigland's avatarPaul Bigland on London, HS2 and home…
Steve Ashford's avatarSteve Ashford on London, HS2 and home…
Chuckster's avatarChuckster on Rolling blog. More Manchester…
ramakrishnanaidu400's avatarramakrishnanaidu400 on Shropshire sojourn. Part …

Archives

  • December 2025
  • November 2025
  • October 2025
  • September 2025
  • August 2025
  • July 2025
  • June 2025
  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • August 2024
  • July 2024
  • June 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • December 2019
  • November 2019
  • October 2019
  • September 2019
  • August 2019
  • July 2019
  • June 2019
  • May 2019
  • April 2019
  • March 2019
  • February 2019
  • January 2019
  • December 2018
  • November 2018
  • October 2018
  • September 2018
  • August 2018
  • July 2018
  • June 2018
  • May 2018
  • April 2018
  • March 2018
  • February 2018
  • January 2018
  • December 2017
  • October 2017
  • September 2017
  • August 2017
  • July 2017
  • June 2017
  • April 2017
  • March 2017
  • February 2017
  • January 2017
  • December 2016
  • November 2016
  • October 2016
  • September 2016
  • July 2016
  • June 2016
  • May 2016
  • April 2016
  • March 2016
  • February 2016
  • January 2016
  • December 2015
  • November 2015
  • October 2015
  • September 2015
  • August 2015
  • July 2015
  • June 2015
  • May 2015
  • April 2015
  • March 2015
  • February 2015
  • January 2015
  • June 2013

Categories

  • 'Green' madness
  • 'Think Tanks'
  • 144e
  • 2005 London bombing
  • 2017 General election
  • 3 peaks by rail
  • 3 Peaks by ral
  • 51M
  • 7/7
  • Abandoned railways
  • Abu Dhabi
  • ACoRP
  • Adam Smith Institute
  • Adrian Quine
  • Advertising
  • Air Travel
  • Aircraft
  • Airports
  • Airshows
  • Allan Cook
  • Alstom
  • Amsterdam
  • Andrea Leadsom MP
  • Andrew Gilligan
  • Andrew Haylen
  • Andy Burnham MP
  • Anti Hs2 mob
  • AONBs
  • Arambol
  • Architecture
  • Art
  • Australia
  • Avanti West Coast
  • Bali
  • Bangkok
  • Bank holidays
  • Barrow Hill
  • beer
  • Belgium
  • Bereavement
  • Berlin
  • Bigotry
  • Birmingham
  • Blists Hill
  • Blue passports
  • Boris Johnson MP
  • Bradford
  • Brazil
  • Brexit
  • Brighouse
  • Brighton
  • British Railways
  • British Railways (BR)
  • Buckinghamshire
  • Buses
  • Byline media
  • Calder Valley
  • Calderdale
  • Cambridge
  • Cambridgeshire
  • Canals
  • Cardiff
  • Carillion
  • Carolyne Culver
  • Censorship
  • Charities
  • Cheryl Gillan MP
  • Cheshire
  • Chester
  • China
  • Chris Packham
  • Claire Perry MP
  • Class 08
  • Class 155
  • Class 180
  • Class 313
  • Class 314s
  • Class 317
  • Class 319
  • Class 320
  • Class 321
  • Class 323
  • Class 365
  • Class 455
  • Class 456
  • Class 507
  • Class 508
  • Class 60s
  • Class 91
  • Climate Change
  • Communications
  • Community
  • Community rail
  • Community Rail Network
  • COP26
  • Corbynwatch
  • Coronavirus
  • Coventry
  • Covid 19
  • CP5
  • Crap journalism
  • Crazy anti Hs2 campaigner of the week
  • Crazy kippers
  • Crewe Hub
  • Crossrail
  • Cuba
  • Cumbria
  • Customs
  • Cyberattacks
  • Cycle India
  • Cycling
  • Dame Bernadette Kelly
  • Dawn
  • Democracy
  • Denmark
  • Derbyshire
  • Desiro City
  • Dewsbury
  • Diary
  • Dispatches
  • Doha
  • Donald Trump
  • Doomed
  • Dorset
  • Down memory lane
  • Duxford
  • East Lancashire Railway
  • East Midlands Railway franchise
  • East Midlands Trains
  • East-West rail
  • Easter fairy stories
  • ECML
  • Economic illiteracy
  • Economics
  • election2015
  • Elon Musk
  • Engineering
  • Environment
  • Essex
  • Eurostar
  • Euston
  • Extinction Rebellion
  • Fake News
  • Festivals
  • Film and TV
  • Flag shaggers
  • Flooding
  • Flora and Fauna
  • Food
  • Food and drink
  • Foot in mouth
  • Gardening
  • GBRf
  • GCRE
  • General election
  • General election 2019
  • General election 2024
  • Georgetown
  • Germany
  • Glasgow
  • Glossop
  • GNGE
  • GNRP
  • Goa
  • Goole
  • Grand Central trains
  • Grant Shapps MP
  • Great Western Railway
  • Greater Anglia franchise
  • Greater Manchester
  • Greece
  • Green issues
  • Green madness
  • Green Party
  • Grok
  • Gt Missenden
  • GTR
  • Guido Fawkes
  • GWML
  • GWR franchise
  • Gwyll Jones
  • Halifax
  • Hampshire
  • Harvil Rd Hs2 protest
  • Harz railway
  • Heathrow 3rd runway
  • High Speed 1
  • High Speed UK
  • History
  • Hitachi
  • Hong Kong
  • House of Lords
  • HS North
  • Hs1
  • Hs2
  • Hs2 Bow Group
  • Hs2 petitions
  • Hs2 Phase 2B
  • Hs2 to Crewe
  • Hs2aa
  • HS2Rebellion
  • HSUK
  • Huddersfield
  • Humberside
  • Humour
  • Hurricane Ophelia
  • Huw Merriman MP
  • Hypocrisy
  • I love my job
  • Imperial College London
  • Imperial War Museum
  • India
  • Indonesia
  • Infrarail
  • Innotrans
  • Internet
  • Iolo Williams
  • Ireland
  • Islamophobia
  • Istanbul
  • Jacob Rees Mogg
  • jakarta
  • Jeremy Corbyn
  • Jeremy Corbyn MP
  • Jo Johnson MP
  • Joanne Crompton
  • Joe Rukin
  • John McDonnell MP
  • John Poyntz
  • Johnathan Bartley
  • Journalism
  • Kanchanaburi
  • Kemi Badenoch
  • Kent
  • Kuala Lumpur
  • Labour election
  • Lancashire
  • Laos
  • Law and order
  • Lazy journalism
  • Leicestershire
  • Levelling up
  • Liam Halligan
  • libel
  • Lilian Greenwood MP
  • Lincolnshire
  • Liverpool
  • LNER
  • Local elections
  • Local elections 2018
  • Lockdown
  • London
  • London Underground
  • Lord Berkeley
  • LRT
  • M62 motorway
  • Major Projects Authority
  • Malaysia
  • Manchester
  • Manchester Airport
  • Manchester Victoria
  • MAPA
  • Mark Keir
  • Marketing
  • Martin Tett
  • Mediawatch
  • Melton Mowbray
  • Memory Lane
  • Merseyrail
  • Merseyside
  • Michael Dugher MP
  • Michael Fabricant MP
  • Mid Cheshire against Hs2
  • Miscellany
  • Modern Railways
  • Monorails
  • Music
  • Musings
  • Mytholmroyd
  • Natalie Bennett
  • National Rail Awards
  • National Trust
  • Nepal
  • Network Rail
  • Never a dull life
  • New Economics Foundation
  • New trains
  • New Year
  • New York
  • New Zealand
  • Newcastle
  • NHS
  • Nigel Farage
  • Norfolk
  • Norland scarecrow festival
  • North Yorkshire
  • Northern Powerhouse
  • Northern Rail
  • Northumberland
  • Norway
  • Nostalgia
  • Nottingham
  • Obituaries
  • Old Oak Common
  • ORR
  • Ossett
  • Our cat, Jet
  • Oxfordshire
  • Pacers
  • Paris terror attack
  • Parliament
  • Pasenger Growth
  • Patrick McLouglin MP
  • Penny Gaines
  • Peter Jones
  • Peterborough
  • Photography
  • Photojournalism
  • Picture of the day
  • Poetry
  • Politics
  • Porterbrook
  • Portugal
  • PR nightmares
  • Preston
  • Protest
  • Public Accounts Ctte
  • Pubs
  • rail ale
  • Rail electrification
  • Rail fares
  • Rail Investment
  • Rail Live 2021
  • Rail Live 2022
  • Rail Live 2024
  • RAIL magazine
  • Rail Moderinsation
  • Rail PR
  • Railfreight
  • Railstaff awards
  • Railtex
  • Railway Benefit Fund (RBF)
  • Railway preservation
  • Railways
  • Rant
  • Religion
  • Reservoir blogs
  • RFEM
  • Richard Wellings
  • Ride India
  • Rishi Sunak
  • Road accidents
  • Rolling blogs
  • ROSCOs
  • Royal Mail
  • Royal Wedding 2018
  • RSPB
  • Rugby Observer
  • Rushbearing
  • SAIP
  • Sarah Green
  • Scores on the doors
  • Scotland
  • Scotrail
  • Sheffield
  • Ships
  • Shrewsbury
  • Shropshire
  • Siemens
  • Signalling
  • Silly season
  • Simon Heffer
  • Simon Jenkins
  • Singapore
  • Sleeper trains
  • Snail mail
  • Social media
  • South West Trains
  • Southport
  • Sowerby Bridge
  • Spectator magazine
  • Sri Lanka
  • St Pancras station
  • Stafford
  • Stamford
  • Station buffets
  • StopHs2
  • Surabaya
  • Surrey
  • Swansea
  • Talgo
  • Teresa May
  • Terrorism
  • Tesla
  • Thailand
  • Thameslink
  • The 'Beast from the East'
  • The BBC
  • The Big 6
  • The Cludders
  • The Daily Express
  • The Economy
  • The end of the line
  • The fog
  • The Grauniad
  • The Great Central railway
  • The Green Party
  • The Guardian
  • The Independent
  • The Labour Party
  • The Moorcock Inn
  • The Piece Hall
  • The PWI
  • The Railway Children
  • The Rodelblitz
  • The USA
  • The Woodland Trust
  • Tilford
  • Tony Allen
  • Torquay
  • Tourism
  • TPE
  • Traffic congestion
  • Trams
  • Trans-Pennine electrification
  • Trans-Pennine Route Upgrade
  • Transport
  • Transport Committee
  • Transport for Wales (TfW)
  • Travel
  • TRU
  • Turkey
  • Twilight years
  • Twitter
  • Twitter (and how not to use it)
  • UK
  • UK steel industry
  • UKIP
  • Uncategorized
  • Uxbridge
  • Vandalism
  • Victoria Prentis MP
  • Virgin Trains
  • Virgin West Coast
  • Vivarail
  • Wales
  • Walking
  • Warwickshire
  • WCML
  • Weather
  • West Yorkshire
  • Wigan
  • Wildlife Trusts
  • Wiltshire
  • Worcester
  • Work
  • World car-free day
  • World War 1
  • World War Two
  • Yorkshire
  • YorkshireStopHs2

Meta

  • Create account
  • Log in
  • Entries feed
  • Comments feed
  • WordPress.com

Blog at WordPress.com.

Privacy & Cookies: This site uses cookies. By continuing to use this website, you agree to their use.
To find out more, including how to control cookies, see here: Cookie Policy
  • Subscribe Subscribed
    • Paul Bigland
    • Join 465 other subscribers
    • Already have a WordPress.com account? Log in now.
    • Paul Bigland
    • Subscribe Subscribed
    • Sign up
    • Log in
    • Report this content
    • View site in Reader
    • Manage subscriptions
    • Collapse this bar
 

Loading Comments...